Project Details
QA Construction was hired as the CSP General Contractor to replace the existing economizer at the Texas State Central Plant for Boiler #2. An economizer uses excess energy the boiler emits through its heating process. This system adds efficiency to the large boilers required at Texas State. QA Construction provided a turnkey replacement of the existing economizer. This process involved removing the existing economizer by crane, installation of new structural steel to support the economizer and flue stack, and control configuration with the existing boiler. Texas State’s boiler number 2 will now function to its highest efficiency saving the University millions in funds.
Market:IndustrialService Provided:Competitive Sealed Proposals